The effect of long lead times for planning of energy efficiency and biorefinery technologies at a pulp mill

Elin Svensson (Institutionen för energi och miljö, Värmeteknik och maskinlära) ; Thore Berntsson (Institutionen för energi och miljö, Värmeteknik och maskinlära)
Renewable Energy (0960-1481). Vol. 61 (2014), p. 12-16.
[Artikel, refereegranskad vetenskaplig]

The pulp and paper industry has many promising opportunities in the biorefinery field. To reach this potential, investments are required in new, emerging technologies and systems solutions which cannot be quickly implemented. In this paper, an approach to model the necessarily long planning times for this kind of investments is presented. The methodology used is based on stochastic programming, and all investments are optimized under uncertain energy market conditions. The uncertain cost development of the emerging technologies is also considered. It is analyzed using scenario analysis where both the cost levels and the timing for market introduction are considered. The effect of long lead times is studied by assuming that no investments can be decided on now and implemented already today, and only investments planned for today can be implemented in, for example, five years. An example is presented to illustrate the usefulness of the proposed approach. The example includes the possibility of future investment in lignin separation, and shows how the investment planning of industrial energy efficiency investments can be guided by using the proposed systematic approach. The example also illustrates the value of keeping flexibility in the investment planning.

Nyckelord: Investment planning, Optimization under uncertainty, Process integration, Lignin separation, Pulp and paper industry



Den här publikationen ingår i följande styrkeområden:

Läs mer om Chalmers styrkeområden  

Denna post skapades 2012-05-15. Senast ändrad 2013-11-26.
CPL Pubid: 157604

 

Läs direkt!


Länk till annan sajt (kan kräva inloggning)


Institutioner (Chalmers)

Institutionen för energi och miljö, Värmeteknik och maskinlära (2005-2014)

Ämnesområden

Energi
Hållbar utveckling
Optimeringslära, systemteori
Kemisk energiteknik
Företagsekonomi

Chalmers infrastruktur

Relaterade publikationer

Denna publikation ingår i:


Optimization of Investments for Strategic Process Integration and Pulp Mill Biorefinery Projects under Uncertainty